If you are a general contractor with a tight schedule or budget, you may want electrical pricing and constructability input before the drawings are finished. Design-assist is one way to get it. It works when everyone agrees in writing who is paid, who is responsible for the design and how the final price is set. This post covers those points and the cases where you should skip it.
Design-assist, design-build and plan-and-spec
In plan-and-spec delivery, also called design-bid-build, the engineer finishes the drawings and contractors price them. Design-build puts design and construction under one contract. Our comparison of design-build and design-bid-build for electrical scopes covers that choice.
Design-assist is a separate idea. Construction Canada magazine, in a December 2018 article on assigning design to constructors, describes it as a procurement method in which a construction contract may be awarded on a best-value basis before the design is complete. A specialty constructor assists the design professional of record, retained through a request for proposals. When this happens before bid, the design professional administers the process, the owner may pay for the input early, and there is a way back to open bidding if the process did not help. The article also cautions against calling design-assist design-build, because design-build describes a contract structure and design-assist describes how the design gets developed. The article covers building design in general, not electrical work in particular.
What the electrical sub contributes early
The article describes a loop: suggest, detail and refine until a solution is reached, then implement, accept and construct. The design-assist participant is responsible for its design contributions, the construction documents it submits, and any mockups and samples.
On an electrical scope, ask for specific items at each design milestone:
- An estimate by system, with the assumptions stated, so you can see what each design choice does to the number
- Equipment lead times and order-by dates, since long-lead electrical equipment drives the schedule
- Constructability notes on service entrance location, routing and coordination with other trades
- Cost-saving options with a price attached, in the form of value engineering that keeps the system's performance
- Utility and permit questions raised early, while the design can still move
Who stays responsible for the design
The Construction Canada article says the design professional of record keeps responsibility for the design in a design-assist process, as with any other subconsultant. It adds that, under licensing guidelines, registered professionals cannot defer, delegate or assign their responsibility for code compliance, and that responsibility for collaborative design stays with the coordinating professional of record. It also warns that deferring design must not become a way to hand an incomplete design to the constructor because the designer lacks time or budget. Deferral is meant for work that needs skills the designer does not have, with the owner informed and in agreement. Check how your own contract treats it.
In this province, Professional Engineers and Geoscientists Newfoundland and Labrador (PEGNL) says licensed members are the only people permitted by law to undertake and assume responsibility for engineering work, and it also licenses companies through a Permit to Practice. Its authentication guideline (September 2024) says a member must stamp, sign and date final documents before they are issued, and that the stamp shows the member has accepted responsibility. It also says field changes that affect an authenticated design should be documented in writing and authenticated in a timely way.
Before design-assist starts, write down:
- Who the engineer of record is, and which firm they work for
- Who stamps the revisions that come from the electrical sub's suggestions
- That the sub's input is advice until the engineer adopts it
PEGNL publishes an online register of licence holders and companies. For when a stamp is needed at all, see when electrical drawings need an engineer's stamp.
Paying for pre-construction input
The article describes pre-construction design-assist as fee-for-service and says that seeking design solutions without paying for them undervalues the service. A useful reference point is the 2025 CCDC 5B, a construction management contract. According to BLG's July 2025 summary, it defines pre-construction services separately from construction services and gives them their own fee model. That contract sits between an owner and a construction manager, so it does not set the terms of an electrical subcontract. The pattern still carries over: price early input as its own line.
Agree these points before work starts:
- The fee or a cap, and what the electrical sub delivers for it
- Who pays it, the owner or you
- What happens to the fee if the sub is awarded the work, and if not
- Who owns the work product, including drawings
- Whether the fee covers a licensed engineer's time or only the contractor's
Keeping pricing competitive after early involvement
In the article, pre-construction design-assist still allows competitive procurement. It puts the final design into the construction documents, either as a single-source specification with no substitutions or as a basis of design that allows substitutions, with a clause requiring the design-assist entity to review substitutions for conformance.
The article treats design-assist after award, managed through a cash allowance, differently. It says the market is assumed to keep prices competitive, but experience shows the approach tends to need additional changes to adjacent assemblies because the solution was not fully integrated. The article is about building assemblies, not electrical systems. Our reading is that the same applies to electrical: involve the sub before bid, not after.
To keep tension in the price:
- Select the design-assist electrical contractor through a documented process with stated criteria.
- Say in the agreement whether the finished package will be open bid, and whether the design-assist sub may bid.
- Ask for estimates by system at each milestone, so you have a benchmark if the work goes out to bid.
- Make sure the design you paid for can go to other bidders.
When design-assist is not worth it
Skip it when:
- The drawings are complete and tender-ready, so there is little left to assist
- Procurement rules require an open tender of finished drawings
- The scope is too small to repay a design fee
- The design team cannot fold the sub's input in before the design is frozen
- Design-assist is being used to pass an incomplete design to the contractor, which the article warns against
How our design-build estimate works
Our design-build estimating offer is built for GCs, developers and owners bidding design-build or design-assist electrical scopes. You send the drawings, specification and schedule. Partial packages are fine, and we tell you what is missing and what we will assume.
- If you already have electrical drawings, we price straight from them with no design fee.
- If the job needs engineering first, our partner professional engineer produces stamped drawings for a fixed fee, quoted per project before any work starts. You approve the fee and pay a deposit before engineering begins.
- If Puffin Power is awarded the electrical work, the fee is credited into our competitive bid. If not, you keep the stamped design.
- You receive a line-item estimate by system with allowances and exclusions stated, crew availability against your schedule, and one point of contact from drawings to commissioning.
- Turnaround is set per package when we quote the fee.