Commercial buildings

Fire alarm verification before occupancy in NL

Plan approval, installation and CAN/ULC-S537 verification of a fire alarm in Newfoundland and Labrador, and how to schedule them ahead of occupancy.

A fire alarm passes through hands that are not on your site every day: a plan reviewer, a verifier and the authority that approves occupancy. This post sets out the order of events in Newfoundland and Labrador and how a general contractor can keep the fire alarm from moving the occupancy date.

Approval, installation and verification

The Fire Protection Services Regulations (NLR 45/12) set the sequence for fire alarm and detection systems in three parts:

  1. Plans for the installation shall be approved by the fire commissioner (section 7(4)).
  2. Systems shall be designed only by qualified persons in accordance with the National Building Code, and every component shall be tested, listed and labelled by a laboratory accredited by the Standards Council of Canada, or otherwise approved by the fire commissioner (section 7(2)).
  3. Installation and verification of newly installed systems shall comply with the National Fire Code of Canada (section 7(3)).

The regulation names the 2015 editions of the national codes, then adopts later editions, and updated referenced standards, six months after publication. Confirm the governing edition with the designer rather than assuming it from an old spec.

The Schedule to the same regulation treats a building as new construction until the authority having jurisdiction approves it for occupancy. Ask that authority, in writing, what it needs in hand before it will approve occupancy.

Plans go to the fire commissioner

The province's Fire and Life Safety Plan Reviews page, under Government Services, says approval of all commercial building plans, including fire prevention and suppression systems, is required under the Fire Protection Services Act. It asks for an application form, three copies of detailed plans and a letter of referral from the municipal council, and lists a separate fee for fire protection systems (fire alarms and sprinklers). Applications go to the email address or nearest office listed there.

The page gives no review time. Ask for the current turnaround and put it in the schedule before equipment is ordered. Treat approval as a gate before rough-in, not a close-out document, and ask whether a change to device locations after approval needs resubmission.

The same page notes that St. John's and Corner Brook conduct their own fire and life safety inspections, and that plan review is completed by the Office of the Fire Commissioner. The City of St. John's building permit page also says it is the property owner's responsibility to request inspections and make sure they are approved, so settle who books them.

What CAN/ULC-S537 verification covers

The regulation ties verification to the National Fire Code but does not name a standard itself. The Canadian standard written for this step is CAN/ULC-S537, Standard for Verification of Fire Alarm Systems. The Standards Council of Canada's database lists the 2019 edition, published July 31, 2019, superseding the 2013 edition. Its scope says it prescribes inspection and test procedures for verifying that the system is installed in conformance with the design and with CAN/ULC-S524, the installation standard, and performs all of its intended functions as designed. It is intended to apply to both required and voluntary installations. Ask the designer which edition the governing code calls up.

The verifier needs the approved design and the as-installed information, and anything not installed, powered or programmed will show up as a deficiency.

The regulation also restricts who may do the work. Section 8(3) says no one may perform maintenance, repair, inspection, testing or verification of an installed system unless, in the fire commissioner's opinion, the person has the tools and test equipment, has passed certification examinations to the commissioner's satisfaction and holds the applicable licences. Ask for the verifier's licence details before you book. The provincial fire services branch also lists licences for the installation and maintenance of fire alarm systems among its responsibilities, so ask the installer too.

Renovations and system extensions

The Schedule defines a modification to include the reconfiguration or extension of any system, and it treats modification as a form of rehabilitation work. Two sections matter for a fit-up that touches the alarm:

  • Section 8(1) of the Schedule: where a rehabilitation work area is in a building the National Building Code requires to have a fire alarm and detection system, the system shall be installed throughout the entire building.
  • Section 8(2) of the Schedule: where a building has no system and the finished work changes the occupancy classification or occupant loading, a system shall be installed throughout the entire building.

Read those with your designer before you price. The alarm scope may be larger than the work area. In St. John's, the City's building permit page lists renovating an office space and occupancy changes as work needing a building permit, so a fit-up that extends the alarm can have a building permit, an electrical permit and a plan review running at once.

Section 5 of the Schedule says that for a rehabilitation project involving multiple adopted codes, the authority and the agencies involved may meet an applicant who asks, before the construction permit application and on payment of any required fees. The codes listed include the Canadian Electrical Code and the National Fire Code. Ask for it when a renovation touches electrical, alarm and egress together.

If the existing system has to come offline in an occupied building, section 8(7) of the regulation puts duties on the person responsible for completing the work. They must immediately notify the fire department and the monitoring station, in writing if the shutdown is expected to exceed 24 hours. They must post notices on all floors by the elevators and at entrances, patrol the area at least once every hour, notify the fire department, monitoring station, occupants and owner when the system is working again, and meet any other shutdown requirements the fire commissioner sets. Put a name beside that duty in the subcontract, and keep tie-ins short.

Who does what on site

The boundary between electrical and fire alarm scope is a common place for work to fall between two trades, as our post on reading electrical exclusions explains. Get written answers to these:

  • Who supplies the panel and devices, and who installs raceway, boxes, wiring and terminations?
  • Who programs the system, and who produces the as-installed device list?
  • Who verifies, who employs them and what licence do they hold?
  • Who arranges the monitoring station connection and notifies it during testing?
  • Which other systems does the design connect to the alarm, such as sprinkler switches, door hold-opens or fan shutdown? Who owns each side of each interface?
  • Who pays for deficiencies found at verification and for a re-verification?

Scheduling verification against occupancy

Work backward from the occupancy date.

  • Ask the verifier and the authority for lead times in writing.
  • Ask the installers to test the system themselves first, so wiring faults are fixed before the verifier arrives.
  • Confirm the verifier can reach every device location, with finishes and ceilings far enough along.
  • Make sure systems the alarm interfaces with are ready, or agree how they will be simulated.
  • Confirm normal power and any backup power the design specifies are live.
  • Hold time in the schedule for a failed item and a retest.
  • Ask the authority whether it needs the verification report before occupancy, and who submits it.

Paperwork worth collecting at handover

File these with the electrical records:

Talk to Puffin Power

Send the electrical and fire alarm drawings through contact. Our design-build estimate is line-item by system, with allowances and exclusions stated, so where the electrical scope meets the fire alarm scope is on paper before award.