If you are the general contractor on a building with HVAC, the line between the mechanical and electrical subcontracts runs through many connections. A rooftop unit, a pump on a drive, a damper that closes on a fire alarm signal: each one needs someone to furnish it, someone to set it, someone to wire power to it and someone to wire its controls. When the documents leave one of those jobs unassigned, both bidders can exclude it in good faith, and you pay to close the gap after award.
Where the gap opens
In MasterFormat, the North American format for organizing construction specifications, HVAC is Division 23, Integrated Automation is Division 25, Electrical is Division 26 and Electronic Safety and Security is Division 28. One air handler can involve all four, and depending on how you split the work, that can mean up to four subcontractors.
Here is a published example from this province. The NL Master Specification Guide for Public Funded Buildings (version 10/22) is, by its user instructions, mandatory for building contracts tendered by the Department of Transportation and Infrastructure. Its HVAC motor section says supplier and installer responsibility for motors, equipment and controls is shown in a Motor, Control and Equipment Schedule on the electrical drawings, with related mechanical responsibility on a Mechanical Equipment Schedule on the mechanical drawings. Its electrical common-work section also points to the drawings. Neither section assigns each item itself. They point to a schedule, so the schedule has to exist and agree on both sets of drawings.
Do not assume a split from another job, since it varies by owner and designer. Check the matrix in your own specifications and drawings, and if the documents refer to a schedule that was not issued, ask for it before bid day.
Furnish, install and wire are different
Four questions sound like one. Who buys and delivers the item? Who sets it in place? Who runs power to it? Who runs its controls? The same master specification answers them differently by item. Its variable frequency drive section makes the controls contractor responsible for installing the drive and the electrical contractor responsible for power wiring. Its motor starter section, which sits in the electrical division, tells the installer to install starters and connect power and control as indicated.
A subcontractor reading only its own scope sees half of that. For every piece of equipment, put one name against each of these:
- Furnish
- Set in place
- Power wiring and disconnect
- Control wiring
- Start-up and testing
Starters, drives and disconnects
Start with the approved submittal, not the equipment schedule. Does the unit arrive with its starter or drive and disconnect built in, or do they ship separately? If they ship separately, someone has to mount, wire and pay for them, and that person may not be the one who bought the unit.
Drives add a line of their own. The NL specification requires certified factory start-up of each drive by an authorized service centre, so ask who pays for that visit and who is on site to receive it. Also ask who wires between the drive and the motor, and who owns the bypass if one is specified.
For disconnects, ask two things: is it furnished with the equipment or separately, and is it shown on the mechanical or the electrical drawings? A disconnect drawn in only one set is easy to miss in the other bid.
Controls and building automation wiring
In the NL specification, the line between controls and electrical is a voltage. The general requirements for the building energy monitoring and control system (EMCS) say the controls contractor supplies the network wiring and the control wiring and conduit at 50 volts or less, and that wire and conduit above 50 volts are by the electrical division. The electrical common-work section draws the same line from the other side. Even so, one section says 50 volts or less and another says below 50 volts, so pin the exact threshold down in an addendum. The controls scope also includes wiring interface coordination for equipment supplied by others.
The same logic shows up in small items. For temperature sensors, the HVAC controls section has the controls division supply, install and wire the sensor, and the electrical division provide only the box and conduit to the ceiling space.
Your documents may draw the line somewhere else. Find where, and then ask three things: who provides line-voltage power to control panels, who provides boxes and conduit for field devices, and who is responsible when a 24-volt circuit and a 120-volt circuit end up in the same enclosure.
Dampers, interlocks and fire alarm ties
Fire alarm ties are where three scopes meet. In this province the fire commissioner approves fire alarm plans, and only a person the commissioner accepts on tools, certification and licensing may verify the system (Fire Protection Services Regulations, sections 7 and 8). The person who verifies the system is not necessarily the person who wired the air handler.
The NL specification gives a sense of the connections. Its fire alarm section lists ventilation unit shutdown among the uses for addressable control modules, and its installation clause includes wiring to the ventilation units identified for shutdown on alarm. Its damper section describes motorized smoke dampers that stay open while powered and close when power is lost, and combination fire and smoke dampers actuated by smoke detection or a fusible link. Each of those is a wire or a power feed that belongs on someone's list.
List every tie as its own matrix line: what signals what, who supplies the relay or module, who wires it, and who attends the verification. Confirm the mechanical contractor is on site when the interlock is tested.
Equipment changes after award
A substitute unit can change amperage, voltage, disconnect size and control points. The NL electrical common-work section requires shop drawings to include wiring diagrams showing interconnection with other sections' work, and a contractor's stamp stating the equipment was coordinated with equipment supplied by other divisions.
Borrow that habit:
- Route every mechanical submittal that changes electrical data to the electrical subcontractor before it is approved.
- Re-issue the matrix with each change.
- Get the price effect in writing before anything is ordered.
Our note on keeping electrical change orders small covers pricing the changes that still happen.
Build the matrix before bid day
- List every piece of mechanical equipment from the schedule, including motors, drives, heaters and dampers.
- For each, record who furnishes, sets, powers and controls it, and who starts and tests it.
- Note the voltage where power and control wiring meet.
- Add every fire alarm and automation tie as its own line.
- Issue the matrix as an addendum so every bidder prices the same split, with the rest of what an electrical estimator needs in a bid package.
- When bids arrive, compare each exclusion list to the matrix. See how to read an electrical subcontractor's exclusions.
The matrix takes little time to make before bid day and a good deal more to reconstruct after both subs have priced around each other. To get the electrical sub's input before the drawings are final, see design-assist electrical.