If you are the general contractor on a job in Newfoundland and Labrador, temporary construction power is a cost and a schedule item that can fall between bids with no clear owner. The electrical bid may exclude it, the utility treats it as a separate service, and in St. John's it has its own permit. This post draws on Newfoundland Power's temporary service checklist (October 2024 edition) and the City of St. John's Electrical Bulletin E-2026-002 (March 2026). Check both for newer versions. If another utility serves your site, ask for its process.
Who carries temporary power on your job
Settle four questions before the electrical subcontract is signed.
- Is temporary power in the electrical bid, and what does it cover: a pole or trailer service, distribution, lighting, a generator?
- Who is the customer on the utility account, and who pays the connection fee and any deposit?
- Who maintains the installation while it is energized?
- Who removes it, and when?
Our guide to reading an electrical subcontractor's exclusions shows how it slips between bids. The utility's charge is worked out per application, so it may not be a known number at bid time. Carry it as a stated allowance with a reconciliation at closeout, worded as in keeping allowances honest.
A separate utility request and account
Newfoundland Power treats a service needed for less than three years as temporary. The customer pays a temporary connection fee: the estimated labour to install and remove the lines and equipment, plus the estimated cost of material that cannot be salvaged. Temporary and permanent service each need their own bill account and technical work request number. Contribution in aid of construction charges may also apply, for example on a site more than 85 metres from existing power lines.
When you request the service, the utility asks what it is for, a construction shack or power for the building itself, and for the electrician's name and phone number. A technologist contacts you within two business days of account setup. Have these ready:
- A survey or real property report and the registered owner's name, so the utility can assess easements
- Voltage and amperage, from your electrician or consultant
- A single-line diagram of the service entrance and metering
- The date you need power
- A site plan
Fees and any deposit are paid before connection. Decide early whose name goes on the account, since the deposit depends partly on credit standing and history with the utility.
Lead time for a temporary service
The checklist gives a range for each step:
- Design of the temporary infrastructure: 1 to 3 weeks
- Approvals with the appropriate agencies: 1 to 6 weeks
- Power line construction: 3 to 6 weeks
- Current transformers and meter, where the service needs them: 3 to 5 days
- Permit, inspection and authorization number to the utility: usually 2 to 3 days
- Service connection: 1 to 2 weeks
If the steps run one after another, design, approvals, line construction and connection alone add up to roughly 6 to 17 weeks. That total is our arithmetic, not a utility commitment. The checklist warns that weather, system maintenance and difficulty obtaining easements can add delay. It also asks that the property be at final grade before the utility's construction phase begins, which ties temporary power to the sequencing in coordinating electrical with civil work. Send the request once the site plan is stable, not at mobilization.
Poles, trailers and meter sockets
Under Newfoundland Power's Service and Metering Guide (Revision 3.0), an overhead temporary service goes on a customer-owned pole built to the utility's standard drawing, or on a service mast on a construction shed or trailer with equivalent safety considerations such as minimum height, guying and CSA conduit. A trailer must be permanently affixed or judged stable by the customer's consultant under the wind and ice loads expected. The inspection authority and the utility assess each arrangement case by case. Underground temporary services may use a padmount transformer or enclosure.
What that means on site:
- The customer keeps the pole plumb and the clearances correct for the life of the service. The utility may disconnect without notice if the attachment is compromised or the agreed term, three years at most, is exceeded.
- Trailer location drives cost. The checklist suggests discussing locations with the technologist, because the right spot can mean less utility infrastructure and less installation and removal labour.
- The checklist says the meter socket is picked up at Newfoundland Power, while the guide has the customer supply standard self-contained sockets. Confirm with the technologist who supplies yours, and mark each socket clearly where a site has several services.
Permits and inspections for temporary power
In the City of St. John's, temporary power has its own permit. The bulletin says one can be issued for a construction site with an approved building application, and that contractors should get the utility's approval before applying. The application lists every power source and piece of distribution equipment, and needs a single-line diagram for any supply above 45 kVA other than a single-phase service of 200 amps or less. Installations must meet the Canadian Electrical Code, Part I, including Section 76 on temporary wiring.
Points that affect schedule and budget:
- A temporary power permit is valid for a maximum of one year. Extensions are at the inspector's discretion and carry a fee.
- Temporary permits not tied to a residential property are charged at the commercial rate on the total value of the work, including renewals.
- The electrical contractor requests inspection before energizing the service and distribution equipment, any generation, and the wiring and devices, then a final inspection once everything has been removed.
The City issues electrical permits only to contractors it has licensed, so ask any electrical subcontractor working in St. John's to confirm its City licence. Our St. John's area page summarizes the process. Outside the City, the provincial Electrical Regulations require a registered electrical contractor to obtain an installation and repair permit from the Government Service Centre before starting, and plans for work other than single-family dwellings go in for review.
Generators need a permit too
In St. John's, every temporary power installation needs an electrical permit, generators included, and generation is inspected before it is energized. Elsewhere in the province, Government Services approval covers generators and transformers as well as wiring.
The bulletin adds that no additional power source may supply a building already connected to utility power unless the inspection authority specifically approves it. Ask your electrical subcontractor who supplies the generator, who applies for its permit, and whether the price assumes a utility temporary service is still needed alongside it.
Cutting over to permanent service
In St. John's, all temporary services supplying a building must be fully disconnected and removed before the permanent service is approved. A cut-over period may be allowed on request, at the discretion of both the inspection authority and the utility, with possible conditions such as on-site supervision by a qualified person and extra labelling. The utility's guide describes a cutover period as a short, agreed window for moving essential loads and life safety systems from one service to another. A request needs a project plan covering the period, the reason and how affected workers will be briefed, a labelling and warning-sign method, and confirmation that disconnecting equipment works.
To keep the handover clean:
- Schedule temporary service removal before the permanent service is due for approval.
- If the building has to stay live through the transfer, ask for a cutover period early.
- Send the utility a written request, email accepted, to remove the temporary service.
- Book the final inspection after removal.